Skip to Content
About UsMediaNewsContact Us

Invest WindsorEssex Logo Invest WindsorEssex Logo

Contact Us
  • Why WindsorEssex
    • Available Land and Buildings
    • Communities
    • Construction and Development
    • Cost of Doing Business and Utilities
    • Data and Reports
    • Education and Training
    • Incentives and Foreign Trade Programs
    • Labour and Workforce
    • Location and Proximity to Markets
    • Quality of Life
    • Recognition and Awards
    • Top Employers
  • How We Help
    • Automobility and Innovation
    • Business Advice and Support
    • Business Expansion and Networking
    • Conferences and Tradeshows
    • COVID Economic Response
    • Incentives and Foreign Trade Programs
    • Small Business and Entrepreneurship
    • Women Entrepreneurship Strategy
  • Site Selection and Data
    • Available Land and Buildings
    • Key Sector Database
    • Data and Reports
    • Doing Business in Canada
    • Foreign Trade Zone Programs
    • Location and Proximity to Markets
    • Location Incentives
    • Moving Here
    • Site Selector Tool
  • Industries
    • Advanced Manufacturing
    • Agriculture and Agri-Tech
    • Key Sector Database
    • Connected and Autonomous Vehicles
    • Information and Communications Technologies
    • Life Sciences
    • Professional Services and Back-Office Operations
    • Transportation and Logistics
    • Zero Emission and Clean Tech
  • About Us
    • Accessibility
    • Board of Directors
    • Careers
    • Contact Us
    • Departments
    • Events Calendar
    • Media
    • Privacy Policy
    • Recognition and Awards
    • Staff Listing
    • Strategic Plan

Province to announce more measures to boost local power capacity and distribution

  • Facebook
  • Twitter
  • LinkedIn
  • Email
Email icon Back to Search
Business news image

Dave Waddell/The Windsor Star

Facing an unprecedented growth of demand for power in Essex and Kent Counties over the next five years, Premier Doug Ford will announce Friday, in addition to investing $1 billion to fast-track the building of five new transmission lines, the province is also prepared to speed up the process for approving the lines.

“Nothing will slow us down as we build the infrastructure that businesses need to create jobs right here in southwestern Ontario,” Ford said in a statement.

The rapidly growing greenhouse industry and the addition of the new $5-billion battery factory and its extensive supply chain, combined with a growing population, will result in a doubling of demand in the region from 1,000 to 2,000 megawatts over the next five years. That’s about 20 times the average rate of growth of demand expected across the rest of the province.

Whether the region would have enough power in the short term to attract the supply chain forming for the LG Energy Solutions/Stellantis battery plant was feared to be one of the obstacles in landing a $2.5-billion LG Chem cathode plant.

However, sources have said talks in recent weeks between the province and local officials about the options available to boost capacity and transmission both in the short and long term have convinced city officials that a lack of power will not be an issue in the region’s attempts to land the LG Chem plant or other facilities.

“While electricity demand is increasing elsewhere in the province, the speed and magnitude of forecasted growth in Southwest Ontario is unique,” said Andrew Dow, the Independent Electricity System Operator’s supervisor media relations and editorial services.

“All options are being used to increase electricity capacity in the region, including generation, transmission, energy efficiency and innovative solutions.”

Officials said talks between the province, IESO and city have been moving rapidly in the past few days.

Among the ideas on the table are extending the new transmission lines from Lakeshore right to the Lauzon Parkway as part of one project rather than following the completion of the initial Lakeshore phase.

Speeding up the environmental assessment process is another measure being discussed.

IESO and local officials are also looking at starting up some dormant generation facilities, including co-generational capacity in the private sector. A list of companies with that capacity is being compiled and an assessment of how long it might take to get those facilities operational is being undertaken.

The province is also looking at incentive programs in areas like Essex County where there are capacity challenges. That could be things like subsidizing placing solar panels on roof tops to boost generation or conservation efforts to reduce load demand.

“The IESO has been actively engaging with communities and businesses in southwest Ontario for several years now and there are multiple efforts underway to support growth,” Dow said.

“These efforts have helped support the greenhouse sector and will ensure support for the recently announced Stellantis facility.”

Email iconSubscribe

Let's Talk

Invest WindsorEssex footer logo

Main Office:

119 Chatham St. W, Unit 100
Windsor, ON N9A 5M7

Phone: 519.255.9200
Toll Free: 1.888.255.9332
Fax: 519.255.9987
Contact Us

AccessibilitySitemapWebsite FeedbackContact UsPrivacy Policy
Follow Us: View our Facebook Page View our Twitter Page View our YouTube Page View our LinkedIn Page View our Instagram Page

© Copyright 2022 Invest WindsorEssex

Browser Compatibility Notification

It appears you are trying to access this site using an outdated browser. As a result, parts of the site may not function properly for you. We recommend updating your browser to its most recent version at your earliest convenience.